The Tennessee Data Processing is an 85,000 square foot multi-level Data Center Facility. This project included two 50MVA redundant fed transformers from the local power  company with 5KV distribution feeds through-out the facility.

tndata1

 

tndata2 

W&T installed eight unit substations distribution within the building to handle the massive power load. Eight parallel generators were installed for backup power and redundant feeds using paralleling switchgear system. The Data floor has a raised floor system to provide access to miles of piping with every piece of equipment receiving redundant feeds from UPS's and Batteries. This building was an extremely fast track schedule and the entire building was substantially completed in nine months. W&T employed more than 100 men on this facility.

The facility was brought on line in 6 months and totally completed in 9 months. The owner has engaged W&T in a maintenance contract.

General Contractor: Tishman Construction